|

It is a legal requirement in Nova
Scotia to obtain a building permit for any construction project. This applies to all
construction projects; from a new home to shopping mall renovations. The building
inspector will review the plans to ensure they meet all applicable National Building Code
requirements, obtain approval from the municipal engineer, and where necessary, the
Departments of Transportation and Environment and the Fire Marshall. The inspector will
conduct on-site inspections at various stages of the construction project to ensure the
building standards are met. The processing of an application takes an average of three
weeks.
In areas where there is a Land Use By-law in
effect, it is also necessary to obtain a development permit. This permit is required for
all new construction and any change in use to an existing structure. It is confirmation
the project is in compliance with the regulations of the Land Use By-law with regards to
the use, lot requirements and any development requirements. Processing time for the
development permit averages a week and it must be issued prior to the issuance of the
building permit. Application for both permits may be made at the same time.
911
CIVIC ADDRESSING
At the time of applying for a building permit for new construction
you should also apply for a 911 civic address. The application can be made either on the
building permit application form or by calling the 911 addressing co-ordinator at the
RCBDPC. We will require the names and civic addresses of your nearest neighbours as well
as a mailing address for you. It may take up to four weeks to issue a new address. The new
number is determined through a measurement from existing addresses to the new address.
INSPECTIONS
Inspections are required for all work for which a building permit
has been issued and the request for the inspections must be made by the applicant as
certain stages of construction are complete. The applicant is informed as to when
inspections are required at the time the permit is issued. The inspections are conducted
by the inspection staff of the District Planning Commission, using the National Building
Code as a reference when evaluating the safety of the project. The following is a list of
inspections which are normally conducted:
| Inspection |
Installations
Required |
| Footer |
- location certificate
required in zoned area
- all step footings to comply
with NBC 1995
|
| Foundation |
- operational drain tile
- damp-proofing
- floor system
to provide lateral support (where applicable)
|
| Framing |
- any underground plumbing
- all support
framing
- plumbing waste
and vent system
|
| Pre-dry wall |
- insulation and vapour barrier
- mechanical
ventilation
|
| Occupancy |
- structure
complete, ready for occupancy
|
BUILDER'S CHECKLIST
This
checklist provides the general process prior to and during construction. You will be
advised by the Building Inspector of the specific requirements at the time of application.
| ü |
Two copies of the site plan or
survey plan |
| ü |
Two complete sets of the
building plans, including foundation plan, floor plan, detail section; plumbing schematic
and where applicable, electrician's application |
| ü |
Completed development permit
(where required) and building permit application |
| ü |
Permit fee submitted with
completed permit applications (refer to Permit Fee Schedule) |
| ü |
Development permit issued
(where applicable) |
| ü |
Department of Transportation
approval (where applicable) |
| ü |
Department of Environment
approval (where applicable) |
| ü |
Public Works approval (where
applicable) |
| ü |
Building permit issued |
| ü |
Building permit posted in a
prominent on-site location |
| ü |
Foundation inspection
requested and completed |
| ü |
Surveyors location certificate submitted (for planned areas
and areas serviced by municipal water and sewer only). |
| ü |
Framing inspection requested and completed |
| ü |
Insulation inspection requested and completed |
| ü |
Occupancy inspection requested and completed |
| ü |
Occupancy permit issued. |
PERMIT FEE SCHEDULE
PLEASE NOTE: fee schedule is subject to change from time to time. Consult with the
Building Inspector when submitting your application |
All Applications must be accompanied by the required fees, cheques or
money orders made payable to the Rural Cape Breton District Planning Commission or
in Victoria County, to the Municipality of the County of Victoria. Refunds of 50% of the
fee are issued only if the application is withdrawn within 30 days of being issued and if
no construction has begun.
Any construction, repair or alteration commenced
without the benefit, of a permit will be subject to double the standard fee. |
Building permits are valid for one year, This may be
extended further upon application for a permit renewal.
For further information, or to obtain a building and/or development permit
application form, please contact the Building Inspector for your area.
|
|
Antigonish
County
Inverness County
Richmond County
Victoria County
Town of Port Hawkesbury
Version francais |